La Vergne's marquee development is Twinning Station (also referenced as the Waldron Station project), a walkable mixed-use town center planned along Waldron and Blair Roads near I-24. It was first approved in 2025 as a roughly 77-acre, roughly $500 million project. As of the August 2026 La Vergne Planning Commission packet, it has grown to about 110 acres with nearly 1,000 proposed residences, and the expanded concept plan and rezoning are under city review.
WHAT IT IS: Twinning Station is a master-planned, mixed-use 'town center' along the west side of Waldron Road near the Interstate 24 interchange in northern Rutherford County, north and south of Blair Road. It is designed as a walkable community combining homes, retail, restaurants, offices, flex-commercial space and neighborhood services, with about 25% open space, pocket parks, village greens, walking trails and sidewalks on both sides of public streets. Plans call for roughly two acres to be graded and donated to the City of La Vergne for a future fire station.
LATEST REVISION (AUGUST 2026): According to the August 25, 2026 La Vergne Planning Commission packet, Twinning Station Partners, LP owns about 110 acres, up from the roughly 76.55 acres in earlier detailed plans. The expansion includes the Hon property at the southwest corner of Blair and Waldron Roads. Equitable Property Company, LLC is seeking approval of a concept plan and a rezoning that would bring more of the property into Planned Density Residential (PDR) zoning. City staff report that the residential count went from 614 units in the original plan to 877 in a second version and 987 in the third.
SIZE / UNIT MIX: The developer's July 27, 2026 Revision 4 summary in the same packet totals 938 residences, slightly fewer than the staff figure. The northern residential area has 16 single-family homes, 42 townhomes and 330 multifamily units. The southern mixed-use area has 330 rental multifamily units, and a 55-and-older section adds 220 residences: 170 active-adult multifamily units, 35 villas and 15 townhomes. Commercial maximums are listed as 94,000 sq ft of retail, 30,000 sq ft of office and 125,000 sq ft of flex-office, and the packet notes that some space could shift between uses. No restaurant, grocery, medical or retail tenants have been announced. Earlier county documentation described a smaller mix of about 578 multifamily units and about 208,000 sq ft of commercial space.
INVESTMENT, JOBS & FISCAL IMPACT: Earlier reporting describes the project as roughly $500 million ('half-billion-dollar'). A separate Industrial Development Board / Rutherford County authorization covers up to about $17.6 million in public infrastructure costs, to be reimbursed through Tax Increment Financing (TIF). That figure is the public-incentive portion, not the total project value. The IDB study projected about 1,513 jobs and a multi-billion-dollar economic impact over 20 years. La Vergne officials have framed the project around recapturing sales-tax 'leakage' to neighboring cities.
TIMELINE, ROADS & STATUS: The project was approved by the Industrial Development Board and Rutherford County in 2025. Earlier reporting targeted a construction start as early as spring 2026 and buildout around 2030. As of the August 2026 packet, the expanded plan was still in the concept-plan and rezoning stage, and the sources reviewed here report no groundbreaking. The plans show Waldron Road as a three-lane roadway in the area, a future connection to Blair Road West, a future realignment of Lake Road, four residential and five commercial entrances, and a committed traffic signal at the main Waldron Road entrance across from Snowdrop Avenue.
OTHER NEARBY PROJECTS (separate): M/I Homes is building The Villages at Woodland Hills, a single-family community on about 40 acres west of I-24 near Woodland Hills Drive. On Murfreesboro Road, the Uptown La Vergne mixed-use development has brought an Aldi-anchored retail center with national tenants. In June 2026, Brentwood-based Legacy Commercial Property announced a Starbucks-anchored retail strip at 101 Floyd Mayfield Drive. A widely cited Fox 17 report of '11,000 homes' counts multiple subdivisions across the Waldron Road corridor and is not Twinning Station's own unit count.
- Project name
- Twinning Station (a.k.a. Waldron Station project)
- Location
- Waldron Road and Blair Road near I-24, La Vergne, Rutherford County, TN
- Owner / applicant
- Twinning Station Partners, LP (owner); Equitable Property Company, LLC (applicant, Aug 2026)
- Size
- ~110 acres in the Aug 2026 rezoning request (up from ~76.55 acres)
- Residences
- 938 in the developer's Rev. 4 table; 987 per the city staff report (incl. 220 age 55+ residences)
- Commercial
- Up to 94,000 sq ft retail, 30,000 sq ft office, 125,000 sq ft flex-office; no tenants announced
- Total investment
- ~$500 million (earlier reporting); $17.6M is the public TIF infrastructure portion only
- Jobs
- ~1,500 projected (IDB study)
- Status
- Approved 2025 (IDB + Rutherford County); expanded concept plan and rezoning in Aug 25, 2026 La Vergne Planning Commission packet (outcome not reported in sources reviewed)
- Timeline
- Earlier target: construction start spring 2026, buildout ~2030; no groundbreaking reported as of Oct 2026